|
| |
|
|
Renovation of Moonlight 265
|
|
|
During the summer 2005 we were more and
more convinced of, that Moonlight should have an overhaul, a bit more than
the usual aft season doing. It wasn't just an easy task, as the boat has
its mooring several hundred kilometres away from our home.
A crane was ordered and Moonlight was by
tortuous roads, - to avoid certain
bridges, - driven to our home and craned over the hedge and put on the
lawn.......and the overhaul could start!
The planned overhaul developed and
rapidly we were in progress with a much larger renovation.
Ole, our son, who serve his
apprenticeship as erector, though with Catarpilar and Mak engines as
speciality, meant that
the cylinder heads on our Perkins surely needed to be looked after.
The cylinder heads were removed. With
free access to pistons and cylinders, a micrometer revealed that the
cylinders were worn oval, which they of course shouldn't be, and this told
us quite a deal about the condition of the rest of the engine. A
co-operation was began with a workmate, who was apprentice at a company,
which amongst others co-operate with Perkins. Both engines had to be
removed from the boat. This wasn't possible unless parts of the glass
fibre bars was cut away, which meant, that after renovation, we could
assemble the engine and test run, and put them back into the boat, still
assembled. By the way, one of the 4 bolts supporting the engine, was
broken.
The engines were totally disassembled and
all parts went through the cleaning machine. It turns out to be high time,
5 piston rings lay in small pieces in the grooves, which in worst case
could result in major engine breakdown. Many parts is replaced, valves and
guides, atomizers, cylinder
liners, water pumps, oil tubes, generators, as well as all bearings. The
engines is assembled using new gaskets and is spray painted. The cost of
this operation is 45000.-Dkk (about 6000€) in spare parts plus some "ice
and pizza" to the two youngsters, who spent many working hours on the
project. But then again, it sounded really good when the engines were
restarted in the test bench!
|
|
|
|
|
 |
Click the photos to enlarge |
|
|
|
|
|
|
|
|
|
|
|
Now, as a great part of the boat was
demounted, the scene was set for renovation of many other things and it
fast spread. The entire cockpit was emptied for all parts which were
able to be unscrewed, cut or torn off, things was grinded, filled and
sprayed. 99% of all wires to instruments, engines, lamps and extras has
been shifted....the only ones which isn't is the wires under the ceiling
lining in fore- and aft cabin. (for your info: it takes about 250 m of
wire for a Moonraker, when you "economize" a bit). New fuses,
instruments and lights are mounted. Price approximate 18000.- DKK (about
2400€).... and it takes a long time!
With the engines removed, there's plenty
of room in the engine compartment, so the old copper tubes for water and
gas can be changed, grinding, cleaning and painting, it all is sound
insulated, and a crane lifts the renewed and newly painted engines back
into the boat.
In the forepeak, the anchor locker has
been made larger, so the chain now problem-free can run in. Some shelves
have been made at top of the sides as well as new side covering. The old
black plastic plates and doors for instruments and fuses have been
replaced with mahogany stain and satin lacquered plywood. The ceiling
lining in the cockpit was renewed, and new throttles and 5 new Morse
cables is mounted.
The shafts had to be lined up, the one
ran out of true 3mm, so the stern tube packing had not to be tight, which
it wasn't. The o-rings in the rudder bearings has been replaced.
|
|
|
|
|
|
 |
|
|
|
|
|
|
|
|
|
At the outer side almost everything
stainless is demounted and electro polished, at a price of 2500.- DKK
(330€), but then it looks almost like new.
I dropped to unscrew guard rail on aft
cabin and handles on cabin roof top, or else I had to demount the ceiling
linings inside.....I had to stop some place.
The entire free board and superstructure
is grounded, filled and sprayed. The vessel has on an earlier stage been
lacquered with one component paint, which normally means, that you can't
use an two component paint unless you remove all the old paint first. This
is huge task, which I wasn't quite crazy about. I poured out my trouble to
a Blake's dealer, who claimed, that if the old paint had been on the
surface for 5-8 years, it is all right to spray two component upon after a
thoroughly grinding and sanding! I had a try and it seemed true,
nothing happened! The vessel then had grinding and filling and was sprayed
with Blake's "Poly best".
Regarding the circumstances, I think I
succeeded quite well. Filler, primer, paint and miscellaneous aids
approximately 7000.- DKK (930€).
|
|
|
|
|
|
 |
|
|
|
|
|
|
|
|
|
The biggest problem, not the one which
took the longest time, but the thing which caused the most speculations
and also made me a bit sour,
was probably the windows, that engineer
who has invented the alu profile for the Moonraker, hasn't thought decades
ahead nor just to the moment the first pane crashes. The entire
framework has to be demounted to shift just a pane! So I had to demount
all frames, cleaned out old silicone and rubber gaskets, grinded and
painted the profiles, which wasn't so bad, but assemble a 3.5m long window
frame on the lawn and put in place, without the whole framework slips so
much, that it become leak, to make a success of it is not an easy task!
Which not all the way succeeded, neither 100% with the large front
windows, so it has to be done over again, preferably before next
summer. I have considered several solutions and I think it all ends up
with changing the alu profiles, so the frame is mounted before the pane is
put in place.
Now, when the hole thing is over, I have
almost forgotten we didn't came to sea 2006 and almost have forgotten how
many hours we have spent on the project. It's really great that our lovely
old Moonraker is in tip top shape without murky wirings and ditto pipes
and tubes.
With the whole family's efforts it
succeeded to test sail a week before the summer holiday's start, of course
some things had to be corrected, which was done, and an early Sunday
morning, in good weather conditions, we leave Esbjerg harbour, up the West
coast of Jutland, and 9 hours later we entered Thyboron harbour. The
a lovely trip - in mixed weather - through the Limfjord, in to Mariager
Fjord, Aarhus bay, and 3 weeks later, 400 miles and approximately 700
Litres of diesel, we enter our mooring in Middelfart.
We have been sailing the summer through
and discovered the things, which have to be corrected: The windows have to
be tightened, the old propellers were so worn, that it wasn't possible to
get them equilibrated and should have been replaced. Port engine is
dripping some oil from so the rear oil ring on the crankshaft has to be
replaced. A set of gaskets is delivered with similar packing boxes for
both engines, which won't do, as the one engine is contra rotating.
Luckily it's a guarantee repair.
We also intended to refurbish the pantry,
and a holding tank stands ready for installation, things we didn't got
done before launching. It's nice to have some things to do during the
winter!
All in all including flybridge tonneau,
bolsters, carpets, flying bridge mast, cables and boxes, echo sounder, gas
fittings and 100 other bits and pieces it all ends up to 125000.- DKK
(16500€) plus an unknown number of working hours.
Now we are just looking forward to the
next summer, where the weather surely will be much better than it
was 2007, (it can't be much worse, can it?) so we all can have a decent
sailing season and may be meet some place out there.
With sailor greetings, Anna & Henning
”Moonlight”
|
|
 |
|